LONGWALL OR NOT?
The large majority of coal mines,  existing or planned, work with the aim of maximum production at minimum cost  and in the majority of cases a correctly designed and well operated longwall  installation is the best means of attaining this objective. Few mines are able  to operate profitably where the ratio of first to second workings is high.
Nevertheless, there are cases where  longwall mining may not be the best option, for example:
	
	- Where  the market for the product is limited; longwalls are not generally successful  with intermittent operation. Though a longwall could be operated continuously  to complete a block and the product stored on surface, it must be remembered  that the coal is paid for when it is mined but does not provide income until  sold or used. Storage on the surface is also an additional cost and in some  cases coal quality deteriorates when stored in air;
 
	
	- Where  the mining lease contains a large number of seam discontinuities (longwall  systems generally do not handle discontinuities of any significant size well)  or other restrictions on the size of longwall blocks such as lease boundaries  or existing workings;
 
	
	- Where surface or sub-surface structures or landforms prohibit subsidence and restrict mining to first workings only
 
	
	- Where  simply raising the large amount of capital required to invest in a longwall is  problematic, at least until some income is available;
 
	
	- Where  the infrastructure available is inadequate to handle high tonnages of coal or  to provide adequate supplies; or
 
	
	- Where  the labour force available will be difficult to train to the standard required  for successful longwall operations (continuous miner operations tend to be  somewhat less demanding).
 
	
Considerations such as those listed  above can dictate at a very early stage that a particular lease is more suited  to being worked by continuous 
miner systems and the large cost of a longwall  installation cannot be justified. It may be necessary to follow the full  planning process to 
prove such a decision but the earlier it can be recognised  the less the resources which are wasted on planning an installation which will  
never occur. Such a mine may never reach the star status of high production  longwall mines but may well provide a satisfactory return on 
investment and  efficient use of a resource. The result of the planning assessment may even be  that the lease should not be worked at all.