bolter miners

 

Bolter Miners

Once support and equipment variations are levelled out any remaining variation in process rates was considered to result from the effectiveness of process application at individual mines. The effect of different mining and equipment configurations is also shown by Figures 13 – 17.

Firstly, the utilisation of a bolter-miner at Mine E results in significantly higher process rates than that achieved with a miner-bolter in the same panel at the mine, while the installation of long roof tendons through the intersections in each roadway significantly impact both continuous miner configurations.


chart

Figure 13: Bolter-Miner Versus Miner- Bolter (Mine E)